Skip to content
CalcGospel 國際數學圖譜
返回

IAL 2020 Jan D1 Q3

A Level / Edexcel / D1

IAL 2020 Jan Paper · Question 3

题目

Problem

The network in Figure 2 shows the activities that need to be undertaken by a company to complete a project. Each activity is represented by an arc and the duration, in days, is shown in brackets. Each activity requires one worker. The early event times and late event times are shown at each vertex.

The total float on activity D is twice the total float on activity E.

(a) Find the values of x, y and z.

(3)

(b) Draw a cascade chart for this project on Grid 1 in the answer book.

(4)

(c) Use your cascade chart to determine a lower bound for the minimum number of workers needed to complete the project in the shortest possible time. You must make specific reference to time and activities. (You do not need to provide a schedule of the activities.)

(2)

(Total 9 marks)

题目中文翻译

图 2 中的网络显示了一家公司完成项目需要进行的各项活动。每项活动用一条弧表示,持续时间(单位:天)显示在括号中。每项活动需要一名工人。每个顶点处显示了最早事件时间和最晚事件时间。

活动 D 上的总时差是活动 E 上总时差的两倍。

(a) 求 x、y 和 z 的值。

(b) 在答案册的 Grid 1 上画出该项目的甘特图。

(c) 使用你的甘特图确定在最短时间内完成项目所需最少工人数的下界。你必须具体引用时间和活动。(你不需要提供活动的时间表。)

解答