Skip to content
CalcGospel 國際數學圖譜
返回

IAL 2021 Jan D1 Q6

A Level / Edexcel / D1

IAL 2021 Jan Paper · Question 6

题目

Problem

The table above shows the activities required for the completion of a building project. For each activity the table shows the duration, in days, and the immediately preceding activities. Each activity requires one worker. The project is to be completed in the shortest possible time.

ActivityDuration (days)Immediately preceding activities
A4
B7
C6
D10A
E5A
F7C
G6B, C, E
H6B, C, E
I7B, C, E
J9D, H
K8B, C, E
L4F, G, K
M6F, G, K
N7F, G
P5M, N

Figure 2 shows a partially completed activity network used to model the project. The activities are represented by the arcs and the numbers in brackets on the arcs are the times taken, in days, to complete each activity.

(a) Complete the network in Diagram 1 in the answer book by adding activities G, H and I and the minimum number of dummies.

(3)

(b) Add the early event times and the late event times to Diagram 1 in the answer book.

(4)

(c) State the critical activities.

(1)

(d) Calculate a lower bound for the number of workers needed to complete the project in the shortest possible time. You must show your working.

(2)

(e) Schedule the activities on Grid 1 in the answer book, using the minimum number of workers, so that the project is completed in the minimum time.

(3)
题目中文翻译

上表显示了完成建筑项目所需的活动。对于每项活动,表显示了持续时间(单位:天)和紧前活动。每项活动需要一名工人。项目应在最短时间内完成。

活动持续时间(天)紧前活动
A4
B7
C6
D10A
E5A
F7C
G6B, C, E
H6B, C, E
I7B, C, E
J9D, H
K8B, C, E
L4F, G, K
M6F, G, K
N7F, G
P5M, N

图 2 显示了用于模拟项目的部分完成的活动网络。活动由弧表示,弧上括号内的数字是完成每项活动所需的时间(单位:天)。

(a) 通过添加活动 G、H、I 和最少数量的虚活动,完成答案本中图 1 的网络。

(b) 将最早事件时间和最迟事件时间添加到答案本中图 1。

(c) 写出关键活动。

(d) 计算在最短时间内完成项目所需的工人数量的下界。必须展示计算过程。

(e) 在答案本的网格 1 上安排活动,使用最少数量的工人,使项目在最短时间内完成。

解答