题目
The network in Figure 1 shows the activities that need to be undertaken to complete a project. Each activity is represented by an arc and the duration of the activity, in days, is shown in brackets. The early event times and late event times are to be shown at each vertex and some have been completed.
Given that
- CHN is the critical path for the project
- the total float on activity B is twice the duration of the total float on activity I
(a) find the value of and show that the value of is 7
(b) Calculate the missing early event times and late event times and hence complete Diagram 1 in your answer book.
Each activity requires one worker, and the project must be completed in the shortest possible time.
(c) Draw a cascade chart for this project on Grid 1 in your answer book, and use it to determine the minimum number of workers needed to complete the project in the shortest possible time. You must make specific reference to time and activities.
题目中文翻译
图 1 中的网络显示了完成项目需要进行的活动。每项活动由弧表示,活动的持续时间(单位:天)显示在括号中。每个顶点处应显示最早事件时间和最迟事件时间,部分已完成。
已知
- CHN 是项目的关键路径
- 活动 B 的总时差是活动 I 总时差持续时间的两倍
(a) 找到 的值并证明 的值为 7
(b) 计算缺失的最早事件时间和最迟事件时间,从而完成答案本中的图 1。
每项活动需要一名工人,项目必须在最短时间内完成。
(c) 在答案本的网格 1 上画出此项目的级联图,并使用它确定在最短时间内完成项目所需的最小工人数量。必须具体说明时间和活动。